SP Energy Networks places great importance on the effect its work may have on the environment and local communities and encourages people to influence and contribute to its plans.

First round of consultation: COMPLETE

The first round of consultation took place between June 8 and August 31, 2015 and sought views on a broad swathe of land (a corridor) within which the project could be built.

We received more than 1,600 items of feedback. This, together with information from further ground and environmental surveys and technical reviews, enabled us to verify the corridor and start identifying potential routes for the KTR Project.

As a direct result of the consultation, we widened the corridor south of Mossdale (where it does not encroach on areas of highest environmental value) to incorporate part of the Laurieston Forest.

Dumfries & Galloway Strategic Reinforcement - Public Exhibitions

Second round of consultation: COMPLETE. 

The second round of consultation took place between October 31 and December 31, 2016 and sought views on our preferred routes for the KTR Project.

WE have reviewed all the feedback and our full report is now available on the Project Documents page