Skip to main content
Accessibility toolbar

Select Language:

Frequently Asked Questions

Question

What timescales should I be working to for my connection?

Answer

The timescales for issuing a connection quotation offer from us receiving all the relevant information are in line with Ofgem Guaranteed Standards. The timescale depends upon the type of connection:

Demand Timescale

  • Single domestic low voltage (LV) service demand connection or alteration (including moving a meter): 5 working days
  • Small project demand connection (domestic developments of 2 - 4 units requiring no LV network extension; or 1 - 4 units requiring LV network extension; or single premises of any kind requiring 1 or 3 phase connections, in all cases involving LV only and whole current metering): 15 working days
  • Other LV connections with LV works: 25 working days
  • Connections involving high voltage (HV) works: 35 working days
  • Connections involving extra high voltage (EHV) works: 65 working days

Generation Timescale

  • Other LV connections with LV works: 45 working days
  • Connections involving high voltage (HV) works: 65 working days
  • Connections involving extra high voltage (EHV) works: 65 working days
 

Hi! I'm the SP Energy Networks System Agent, can I help you?