Industrial & Commercial

SP Energy Networks can help with your industrial and commercial connections requirements.  Our team will assist you from start to finish, getting you connected safely and working to a high standard every time.

New Supply 1 - 20 plots

New Supply (1 - 20 plots)

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
35 days*30 days*£74,303Timelines on request

New Supply, over 20 plots and greater 70kVA

New Supply, over 20 plots and greater 70kVA

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
35 days*30 days*£172,308Timelines on request

Alteration to Point of Connection

Alteration to Point of Connection

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
35 days*8 days*£5639Timelines on request

Metered Disconnection (single plot)

Metered Disconnection (single plot)

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A14 days*£6801Timelines on request

Metered Disconnection (more than 1 plot)

Metered Disconnection (more than 1 plot)

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A26 days*£9331Timelines on request

New Temporary Supply

New Temporary Supply

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
25 days*17 days*£26,909Timelines on request

New Un-metered Supply - New highway

New Un-metered Supply - New highway

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A12 days*£2585Timelines on request

New Un-metered Supply - Existing highway

New Un-metered Supply - Existing highway

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A13 days*£9295Timelines on request

Upgrade (additional load)

Upgrade (additional load)

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
25 days*27 days*£61,379Timelines on request

NRSWA Diversion

NRSWA Diversion

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A19 days*£50,026Timelines on request

Diversion

Diversion

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A19 days*£34,677Timelines on request

Sub-Station Stand by

Sub-Station Stand by

 

Guaranteed StandardsAverage time to receive a quoteAverage price
ex VAT from Oct to now
Average time to get
a connection from payment
N/A2 day*£42620 days*

* Please note that the time quoted as "days" refers to working days from when we receive an application form with all of the required information.