SP Energy Networks can help with your industrial and commercial connections requirements. Our team will assist you from start to finish, getting you connected safely and working to a high standard every time.
New Supply 1 - 20 plots
New Supply (1 - 20 plots)
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| 35 days* | 30 days* | £74,303 | Timelines on request |
New Supply, over 20 plots and greater 70kVA
New Supply, over 20 plots and greater 70kVA
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| 35 days* | 30 days* | £172,308 | Timelines on request |
Alteration to Point of Connection
Alteration to Point of Connection
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| 35 days* | 8 days* | £5639 | Timelines on request |
Metered Disconnection (single plot)
Metered Disconnection (single plot)
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 14 days* | £6801 | Timelines on request |
Metered Disconnection (more than 1 plot)
Metered Disconnection (more than 1 plot)
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 26 days* | £9331 | Timelines on request |
New Temporary Supply
New Temporary Supply
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| 25 days* | 17 days* | £26,909 | Timelines on request |
New Un-metered Supply - New highway
New Un-metered Supply - New highway
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 12 days* | £2585 | Timelines on request |
New Un-metered Supply - Existing highway
New Un-metered Supply - Existing highway
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 13 days* | £9295 | Timelines on request |
Upgrade (additional load)
Upgrade (additional load)
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| 25 days* | 27 days* | £61,379 | Timelines on request |
NRSWA Diversion
NRSWA Diversion
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 19 days* | £50,026 | Timelines on request |
Diversion
Diversion
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 19 days* | £34,677 | Timelines on request |
Sub-Station Stand by
Sub-Station Stand by
| Guaranteed Standards | Average time to receive a quote | Average price ex VAT from Oct to now | Average time to get a connection from payment |
| N/A | 2 day* | £426 | 20 days* |
* Please note that the time quoted as "days" refers to working days from when we receive an application form with all of the required information.