Moving your Existing Supply (Service Alteration)

If you're carrying out modifications to your premises and need to move your electricity meter within 2 metres on the same wall, you should contact your electricity supplier – that’s the company you pay your electricity bill to - and they’ll be able to assist.

If however you want to move your existing connection point and meter to a new location,  SP Energy Networks is here to help.

There are a number of things you will need to consider, the information below will help guide you through the process.

Moving your meter and connection point (1 to 4 plots)

Guaranteed Standards Average time to receive a quote Average price
ex VAT from Oct to now
Average time to get
a connection from payment
5 days* 5 days* £783 27 days*

For more information watch our video on Moving your connection point and electricity meter.

Please note that we cannot offer a custom cost estimate for flatted properties. To receive a quotation please select the "Apply for a Quote" button below.