Branxton to Braxbess 400/132kV Collector Substation Works
This Eligibility Letter submission made to Ofgem sets out SP Transmission’s (SPT) plans to provide additional transmission infrastructure in the Branxton area to facilitate the connection of contracted Battery Energy Storage System (BESS) developments.
These works comprise: (i) the installation of a new 400kV SF6-free Gas Insulated Switchgear (GIS) bay at Branxton 400kV Substation; (ii) an approximate 2.15km 400kV cable circuit from Branxton Substation to the new “Braxbess” 400/132kV Collector substation located at the User’s site; and (iii) the establishment of Braxbess 400/132kV Collector substation, equipped with two 400/132kV 360MVA transformers.
The works are currently programmed to commence and be completed in the RIIO-T3 period.
The investment will build upon the wider Branxton network development, enabling the efficient and coordinated connection of energy storage projects while maximising the use of shared transmission infrastructure and supporting wider network capacity requirements.
Full justification for the preferred investment option is presented within this Eligibility Letter submission, together with a detailed description of the proposed solution. This is consistent with the requirements of Special Licence Condition (SpC) 3.18 (Load Re-opener and Price Control Deliverable) and the associated guidance documents, including the Load Re-opener Guidance and Submission Requirements and the Re-opener Guidance and Application Requirements.
Redactions have been made for this published document due to the sensitivity of the content as it includes confidential information with commercial sensitivity.
Click here to view the full Branxton to Braxbess 400/132kV Collector Substation Eligibility Letter (redacted)
Click here to view the Branxton to Braxbess 400/132kV Collector Substation Eligibility Letter Redaction Justification table